Since the Building Safety Act 2022 came into force, the construction industry, including lift professionals, has had to adapt to a new and more rigorous regulatory landscape.
Anyone working on Higher-Risk Buildings (HRBs) – defined as residential buildings at least 18 metres or seven storeys high, must now secure approval from the Building Safety Regulator (BSR) at key stages of a project. This involves passing three statutory gateways before a building can be designed, constructed and occupied.
Understanding how these gateways work, and why they matter, is essential to deliver safe, compliant buildings without costly redesigns or delays.
Who is the Building Safety Regulator?
Before we dive into the Gateways, let’s first look at the role of the Building Safety Regulator:
• Established under the Building Safety Act 2022, the BSR sits within the Health and Safety Executive (HSE).
• As of 1 October 2023, the BSR became the Building Control Authority for HRBs, meaning it oversees building control approval, inspection regimes, and compliance enforcement for these developments.
• This marks a departure from the pre-existing system where local authorities or private approved inspectors handled building control.
The overarching aim of the BSR is to raise safety standards across the lifecycle of HRBs, ensuring fire and structural safety are not an afterthought but a core part of design, construction, and occupation.
The Three Gateways
At the core of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 are three statutory gateway stages that Higher-Risk Building (HRB) projects must pass through before they can progress. These stages are designed to embed safety at every point in a building’s lifecycle and act as formal hold points for approval.
They take place:
• at the planning application stage (Gateway 1)
• before building work begins (Gateway 2)
• when building work is complete, before occupation (Gateway 3)
Starting construction without BSR approval, or occupying a building without final sign-off, is a criminal offence and may result in enforcement action by the regulator.
Gateway 1 – Planning Gateway
This is the earliest stage and arguably one of the most critical. It operates at the planning application stage and ensures that key fire safety considerations are addressed before planning permission is granted.
How it works:
• Developers submitting planning applications for HRBs must include a fire safety statement explaining how fire safety has been considered in the design and layout.
• Once reviewed, the BSR advises the local planning authority on fire safety matters relevant to planning decisions.
• This early engagement helps identify and address safety considerations, such as escape routes, fire service access, water supplies and overall site layout, at the outset of the design process.
Why it matters:
Embedding fire safety into planning helps avoid costly redesigns later and aligns planning decisions with long-term safety outcomes. It also sets the tone for the remaining gateways by ensuring safety is built in from the start.
Gateway 2 – Pre-Construction Approval
Once planning permission has been granted, the next hurdle is before work can begin on site, and this can only begin once the developer has secured building control approval from the BSR. The regulator has a 12-week period to determine the application from the date it is received.
Key requirements:
This stage requires stringent documentation and detailed assessments to ensure full compliance with building regulations. This includes a mandatory reporting plan, a competence declaration, construction control plan, change control plan, fire and emergency file, and a building regulations compliance statement.
Site inspections:
Once approval has been granted by the BSR, various inspections, both at the onset and during construction will be carried out. During these inspections information or evidence might be requested to prove compliance with building regulations.
This stage can be a challenge for many due to the amount and detail of each document, however it is important that enough information and the right information is provided to meet compliance.
Gateway 3 – Pre-Occupation Sign Off
The final gateway comes at the end of construction, before the building can be occupied.
How it works:
• Developers must submit a completion certificate application to the BSR, along with all necessary evidence showing that the building complies with building regulations.
• There is an eight-week determination period from receipt of the completion certificate application.
• The BSR will assess this evidence and, if satisfied, will issue a building completion certificate. At this point the building’s Principal Accountable Person must register with the BSR.
• The building can then be legally occupied.
Gateway 3 shifts the culture by elevating completion certificates from a formality to a robust final test of safety and compliance. This ensures that homes are safe and ready to be occupied.
The introduction of the Building Safety Regulator and the Gateway process represents a fundamental shift in how Higher-Risk Buildings are designed, delivered and signed off.
For lift professionals, this means safety, competence and documentation can no longer sit in the background. Lift systems play a critical role in a building’s overall fire and life safety strategy, supporting evacuation, firefighting access and resident safety, and will increasingly come under scrutiny at every stage of the Gateway process.
LiftSafe supports building owners and dutyholders by helping them identify qualified, competent and independently vetted lift engineers, giving confidence they are working with the right professionals. It also enables engineers to evidence their skills, demonstrate competence and showcase their commitment to industry best practice.